SPT is exact here because the scheduling model is deliberately small.
highlighted = computed this step
Exact improvement
The total-completion-time improvement is 3.
improvement=3
Simple scope
The model has one machine, all jobs ready, no setup, and no preemption.
single machine, all ready, no setup
Not modeled
It does not model due dates, release dates, setup times, parallel machines, priorities, or uncertainty.
outside this model: due dates and uncertainty
Honesty note
SPT is exact for this all-ready single-machine total-completion-time objective. It does not model due dates, release dates, setup times, parallel machines, priorities, or uncertainty. Pixel positions are rounded for layout; every processing time, completion time, total, and average is exact.