Average flow time is total completion time divided by the number of jobs.
Original average
Original average flow time is 13/3.
original average=13/3
SPT average
SPT average flow time is 10/3.
SPT average=10/3
Same comparison
Average flow time ranks these orders the same way because both averages divide by 3 jobs.
same denominator=3
Average note
Average flow time is exact here because every job is ready at time zero.
all-ready average flow time