Before crashing, recompute the path lengths and identify the controlling path.

highlighted = computed this step

Path A-B-D

Path A-B-D has baseline length 8.

TABD=8T_{ABD}=8
Project crashing tableThe table recomputes path lengths after each displayed crash.project crashing tabledeadline 6activity crash dataactnormalmaxcost/dayA213B422C315D214path lengths after each recomputestateA-B-DA-C-Dcostbaseline8*70crash B7*7*2crash D6*6*6asterisk marks a recomputed critical pathdisplayed plan cost 6exact minimum cost 5final duration 6recompute critical paths after every crash

Path A-C-D

Path A-C-D has baseline length 7.

TACD=7T_{ACD}=7
Project crashing tableThe table recomputes path lengths after each displayed crash.project crashing tabledeadline 6activity crash dataactnormalmaxcost/dayA213B422C315D214path lengths after each recomputestateA-B-DA-C-Dcostbaseline8*70crash B7*7*2crash D6*6*6asterisk marks a recomputed critical pathdisplayed plan cost 6exact minimum cost 5final duration 6recompute critical paths after every crash

Baseline critical path

The longer baseline path is A-B-D, so it controls the project finish.

baseline critical path=ABD\text{baseline critical path}=A-B-D
Project crashing tableThe table recomputes path lengths after each displayed crash.project crashing tabledeadline 6activity crash dataactnormalmaxcost/dayA213B422C315D214path lengths after each recomputestateA-B-DA-C-Dcostbaseline8*70crash B7*7*2crash D6*6*6asterisk marks a recomputed critical pathdisplayed plan cost 6exact minimum cost 5final duration 6recompute critical paths after every crash

Deadline gap

The deadline is shorter than the baseline duration, so the displayed plan needs a reduction.

baseline exceeds deadline\text{baseline exceeds deadline}
Project crashing tableThe table recomputes path lengths after each displayed crash.project crashing tabledeadline 6activity crash dataactnormalmaxcost/dayA213B422C315D214path lengths after each recomputestateA-B-DA-C-Dcostbaseline8*70crash B7*7*2crash D6*6*6asterisk marks a recomputed critical pathdisplayed plan cost 6exact minimum cost 5final duration 6recompute critical paths after every crash