Expected project paths are exact sums of expected activity times.
Path A-B-D
Path A-B-D has expected length 7.
Path A-C-D
Path A-C-D has expected length 19/3.
A−C−D=19/3
Compare paths
The first path is longer in expected time, because 7 is greater than 19/3.
Path note
Expected path length is a sum of expected activity times along that path.
path length equals exact sum