Each branch activity gets its own exact expected time.
B expected time
B's expected time is 3.
C expected time
C's expected time is 7/3. Interpretation: this branch has a fractional expected activity time.
D expected time
D's three estimates are equal, so its expected time is 2.
Expected-time note
These are activity expected times, not promised calendar durations.
expected activity times only