Each branch activity gets its own exact expected time.

highlighted = computed this step

B expected time

B's expected time is 3.

EB=3E_B=3
Expected activity timesExpected times are recomputed from the three estimates.expected activity timesoptimisticmost likelypessimisticexpectedA1232B2343C1257/3D2222

C expected time

C's expected time is 7/3. Interpretation: this branch has a fractional expected activity time.

EC=7/3E_C=7/3
Expected activity timesExpected times are recomputed from the three estimates.expected activity timesoptimisticmost likelypessimisticexpectedA1232B2343C1257/3D2222

D expected time

D's three estimates are equal, so its expected time is 2.

ED=2E_D=2
Expected activity timesExpected times are recomputed from the three estimates.expected activity timesoptimisticmost likelypessimisticexpectedA1232B2343C1257/3D2222

Expected-time note

These are activity expected times, not promised calendar durations.

expected activity times only\text{expected activity times only}
Expected activity timesExpected times are recomputed from the three estimates.expected activity timesoptimisticmost likelypessimisticexpectedA1232B2343C1257/3D2222