PERT expected time is exact arithmetic, not a finish-date promise.
highlighted = computed this step
Expected only
The displayed project time 7 is an expected-time calculation.
expected time=7
Not probability
This does not compute the probability of meeting a date.
no deadline probability
Not simulation
This does not simulate finishes, model correlation, or replace schedule risk management.
no simulation or risk replacement
Honesty note
PERT expected activity times and expected path lengths are model arithmetic. This does not promise finish dates, compute probability of meeting a date, model correlation, or replace schedule risk management. Pixel positions are rounded for layout; every displayed estimate, expected time, and path length is exact.
exact arithmetic inside a PERT expected-time model