PERT expected time is exact arithmetic, not a finish-date promise.

highlighted = computed this step

Expected only

The displayed project time 7 is an expected-time calculation.

expected time=7\text{expected time}=7
PERT scopeThe project-time result is exact arithmetic inside the pinned model.expected times onlytimeproject7A-B-D7A-C-D19/3

Not probability

This does not compute the probability of meeting a date.

no deadline probability\text{no deadline probability}
PERT scopeThe project-time result is exact arithmetic inside the pinned model.expected times onlytimeproject7A-B-D7A-C-D19/3

Not simulation

This does not simulate finishes, model correlation, or replace schedule risk management.

no simulation or risk replacement\text{no simulation or risk replacement}
PERT scopeThe project-time result is exact arithmetic inside the pinned model.expected times onlytimeproject7A-B-D7A-C-D19/3

Honesty note

PERT expected activity times and expected path lengths are model arithmetic. This does not promise finish dates, compute probability of meeting a date, model correlation, or replace schedule risk management. Pixel positions are rounded for layout; every displayed estimate, expected time, and path length is exact.

exact arithmetic inside a PERT expected-time model\text{exact arithmetic inside a PERT expected-time model}
PERT scopeThe project-time result is exact arithmetic inside the pinned model.expected times onlytimeproject7A-B-D7A-C-D19/3