The expected critical path is the path with the longest expected length.

highlighted = computed this step

Longer path

A-B-D has expected length 7, which is longer than the other path's 19/3.

7>19/37>19/3
Expected critical pathThe chart marks the path with the longest expected length.expected critical pathexpected project time 7AE=2o,m,p 1,2,3BE=3o,m,p 2,3,4CE=7/3o,m,p 1,2,5DE=2o,m,p 2,2,2A-B-D = 7 criticalA-C-D = 19/3

Expected critical path

The expected critical path is A-B-D.

expected critical path=ABD\text{expected critical path}=A-B-D
Expected critical pathThe chart marks the path with the longest expected length.expected critical pathexpected project time 7AE=2o,m,p 1,2,3BE=3o,m,p 2,3,4CE=7/3o,m,p 1,2,5DE=2o,m,p 2,2,2A-B-D = 7 criticalA-C-D = 19/3

Expected project time

The expected project time is 7.

expected project time=7\text{expected project time}=7
Expected critical pathThe chart marks the path with the longest expected length.expected critical pathexpected project time 7AE=2o,m,p 1,2,3BE=3o,m,p 2,3,4CE=7/3o,m,p 1,2,5DE=2o,m,p 2,2,2A-B-D = 7 criticalA-C-D = 19/3

Critical note

Critical here means longest expected path in this small model.

longest expected path\text{longest expected path}
Expected critical pathThe chart marks the path with the longest expected length.expected critical pathexpected project time 7AE=2o,m,p 1,2,3BE=3o,m,p 2,3,4CE=7/3o,m,p 1,2,5DE=2o,m,p 2,2,2A-B-D = 7 criticalA-C-D = 19/3