The expected critical path is the path with the longest expected length.
Longer path
A-B-D has expected length 7, which is longer than the other path's 19/3.
Expected critical path
The expected critical path is A-B-D.
expected critical path=A−B−D
Expected project time
The expected project time is 7.
expected project time=7
Critical note
Critical here means longest expected path in this small model.
longest expected path