The cycle-time snapshot uses exact ideal cycle time and counted units.

highlighted = computed this step

Ideal Cycle

Ideal cycle time is 2 minutes per unit.

ideal cycle=2\text{ideal cycle}=2
OEE cycle-time snapshotThe chart recomputes the factors, product, and what-if before drawing.OEE cycle-time snapshotOEE = 3/4 x 3/4 x 8/9 = 1/2planned timedowntime 30operating 90planned 120availability3/4performance3/4quality8/9factornumeratordenominatorvalueavailability901203/4performance901203/4quality40458/9what-if downtime 20; availability 5/6; OEE 5/9deterministic snapshot only

Unit Counts

Total units are 45 and good units are 40.

total units and good units are counted inputs\text{total units and good units are counted inputs}
OEE cycle-time snapshotThe chart recomputes the factors, product, and what-if before drawing.OEE cycle-time snapshotOEE = 3/4 x 3/4 x 8/9 = 1/2planned timedowntime 30operating 90planned 120availability3/4performance3/4quality8/9factornumeratordenominatorvalueavailability901203/4performance901203/4quality40458/9what-if downtime 20; availability 5/6; OEE 5/9deterministic snapshot only

Planned-Time Ideal Units

The planned-time ideal output is 60 units.

planned timeideal cycle=60\frac{\text{planned time}}{\text{ideal cycle}}=60
OEE cycle-time snapshotThe chart recomputes the factors, product, and what-if before drawing.OEE cycle-time snapshotOEE = 3/4 x 3/4 x 8/9 = 1/2planned timedowntime 30operating 90planned 120availability3/4performance3/4quality8/9factornumeratordenominatorvalueavailability901203/4performance901203/4quality40458/9what-if downtime 20; availability 5/6; OEE 5/9deterministic snapshot only