When demand is below the bottleneck, output follows demand exactly.
Demand
Demand is 3 units per hour, below the line capacity.
demand=3
Feasible output
The process can output 3 units per hour, so all demand is feasible.
output=3
No unmet demand
Unmet demand is 0 units per hour.
unmet=0
Utilization snapshot
The utilizations are Prep 1/2, Pack 3/4, and Ship 3/8.
utilizations are exact fractions