Takt time starts with exact available production time and daily demand.

highlighted = computed this step

Available time

Available production time is 480 minutes per day.

available time=480\text{available time}=480
Takt inputsThe deterministic example starts with available time and daily demand.takt inputsvalueavailable time480demand120

Demand

Demand is 120 units per day.

demand=120\text{demand}=120
Takt inputsThe deterministic example starts with available time and daily demand.takt inputsvalueavailable time480demand120