The Critical Path
The Critical Path
The critical path is the zero-slack longest path through the project DAG. In this example, the marked activities determine the project duration. The lesson connects the table interpretation to the graph: zero slack in the schedule becomes a critical route through the dependency network.
Critical activities
There are 4 critical activities. Why: each has zero slack in the recomputed schedule. Interpretation: these are the activities that currently control the modeled finish.
Zero slack path
The slack values on A, C, E, and F are all 0. Why: delaying any one of them delays the project finish. Their zero slack is the schedule signal, not a theme or drawing convention.
Critical path duration
The critical path duration is 11. Why: it matches the project duration from the forward pass. Interpretation: the longest path is the reason the whole modeled project cannot finish earlier.
Diagram note
The graph marks the recomputed critical tasks and critical precedence arcs by role. The same exact schedule table determines those marks, so the diagram is evidence rather than decoration. Pixel positions are rounded for layout; every number shown is exact.