The displayed plan crashes shared activity D so both displayed paths reach the deadline.
Crash D
The displayed plan crashes shared activity D by 1 day.
D crash cost
The added D cost is 4.
added D cost=4
Final lengths
After D is shortened, both displayed paths have length 6.
TABD=TACD=6
Displayed cost
The displayed plan cost is 6.
displayed cost=6