A single demand change can use up the remaining slack.

highlighted = computed this step

B Demand What-If

The what-if raises product B demand to 30 units.

what-if B demand=30\text{what-if B demand} = 30
B demand what-ifThe table recomputes load, utilization, and slack after B demand changes.B-demand what-ifvalueB demand30A load60B load90total load150utilization1slack0

What-If Load

The recomputed total load is 150 minutes.

60+90=15060 + 90 = 150
Product mix loadThe chart compares the base mix with the B-demand what-if.product mix capacity loadavailable 150 min; base load 120; slack 30caseA loadB loadtotalutilizationslackbase60601204/530what-if609015010baseA load 60B load 60slack 30base utilization 4/5; total load 120what-ifA load 60B load 90what-if utilization 1; total load 150what-if load 150; utilization 1; slack 0deterministic product-mix capacity arithmetic only

What-If Slack

Utilization becomes 1 and slack becomes 0.

what-if utilization=1what-if slack=0\text{what-if utilization} = 1\quad\text{what-if slack} = 0
Product mix loadThe chart compares the base mix with the B-demand what-if.product mix capacity loadavailable 150 min; base load 120; slack 30caseA loadB loadtotalutilizationslackbase60601204/530what-if609015010baseA load 60B load 60slack 30base utilization 4/5; total load 120what-ifA load 60B load 90what-if utilization 1; total load 150what-if load 150; utilization 1; slack 0deterministic product-mix capacity arithmetic only