Each activity has optimistic, most likely, and pessimistic estimates.
Optimistic
A's optimistic estimate is 1. It is the small estimate in this pinned row.
Most likely
A's most likely estimate is 2.
Pessimistic
A's pessimistic estimate is 3.
C row
C has estimates 1, 2, and 5. This row will produce a fractional expected time.
(oC,mC,pC)=(1,2,5)