OEE starts by separating planned production time from downtime.

highlighted = computed this step

Planned time

Planned production time is 480 minutes.

planned time=480\text{planned time}=480
OEE inputsThe OEE example starts with exact time, rate, and output data.OEE inputsvalueplanned time480downtime60ideal rate2actual output700good output665

Downtime

Downtime is 60 minutes.

downtime=60\text{downtime}=60
OEE inputsThe OEE example starts with exact time, rate, and output data.OEE inputsvalueplanned time480downtime60ideal rate2actual output700good output665

Operating time

Operating time is 420 minutes.

48060=420480 - 60 = 420
OEE inputsThe OEE example starts with exact time, rate, and output data.OEE inputsvalueplanned time480downtime60ideal rate2actual output700good output665