A balanced what-if removes idle time in this exact pinned snapshot.

highlighted = computed this step

Balanced Loads

The what-if uses cycle 4 and each station load is 4.

loads=4,4,4\text{loads} = 4,4,4
Balanced what-ifThe table recomputes available time, idle time, efficiency, and delay.balanced what-ifvaluecycle4available12idle0efficiency1delay0

What-If Idle

The balanced what-if has idle time 0.

what-if idle=0\text{what-if idle} = 0
Balanced lineThe chart compares the base station loads with the balanced what-if.balanced line what-ifbase efficiency 4/5; delay 1/5basecycle 5; available 15; idle 3station 1load 5idle 0station 2load 4idle 1station 3load 3idle 2work 12; efficiency 4/5; delay 1/5what-ifcycle 4; available 12; idle 0station 1load 4idle 0station 2load 4idle 0station 3load 4idle 0work 12; efficiency 1; delay 0deterministic station-load arithmetic only

What-If Efficiency

Efficiency becomes 1 and delay becomes 0.

efficiency=1delay=0\text{efficiency} = 1\quad\text{delay} = 0
Balanced lineThe chart compares the base station loads with the balanced what-if.balanced line what-ifbase efficiency 4/5; delay 1/5basecycle 5; available 15; idle 3station 1load 5idle 0station 2load 4idle 1station 3load 3idle 2work 12; efficiency 4/5; delay 1/5what-ifcycle 4; available 12; idle 0station 1load 4idle 0station 2load 4idle 0station 3load 4idle 0work 12; efficiency 1; delay 0deterministic station-load arithmetic only