The policy safety factor adds a deterministic allowance to lead-time demand.
Lead-time demand
Lead-time demand is 40 units.
lead-time demand=40
Safety factor
The safety factor is 1/4.
safety factor=1/4
Safety allowance
Safety allowance is 10 units.
40×1/4=10