Due dates are recomputed from trigger date plus exact calendar days. Honesty note: toy contract model; jurisdictions vary; the pinned first step states the as-of date; enforceability and breach require legal review; not legal advice.

highlighted = computed this step

Contract model honesty note

Honesty note: toy contract model; jurisdictions vary; as of June 24, 2026; enforceability and breach require legal review; not legal advice; status trace is not a breach conclusion.

toy contract as of June24,2026\text{toy contract as of }June 24, 2026

Due rule is an exact count

The toy clause uses a stated calendar-day count from Toy Contract sec. 2.1. The model excludes the trigger day and then counts forward.

exclude trigger day, then count\text{exclude trigger day, then count}

Example trigger and count

The trigger date is June 1, 2026. The authored due-days value is 3.

due days=3\text{due days}=3

The count governs the due date

Excluding the trigger day, 3 calendar days after June 1, 2026 gives June 4, 2026.

due date=June4,2026\text{due date}=June 4, 2026

Diagram note

The diagram displays the recomputed due date in the obligation row. It is a toy clock, not filing or contract advice.

date is recomputed\text{date is recomputed}

Jurisdiction: US; as of 2026-06-24; not legal advice; Code encodes the stated-rule interpretation.

Due date rulerowfieldvaluescopenoteDue date rule; jurisdictions vary; enforceability and breach require legal review; not legal advice; status trace is not a breach conclusion.statusvocabularylate,not_triggered,pending,satisfied,unknownclause deliveryrank1clause deliverystatuspendingclause deliverytriggeredTrueclause deliverytrigger2026-06-01clause deliverydue2026-06-04clause deliveryperformancenoneclause deliverydaysLate0clause deliveryciteToy Contract sec. 2.1

Summary

A due-date rule is inspectable when the trigger date, count, and computed due date are all visible.

show inputs and computed date\text{show inputs and computed date}