A bottleneck improvement can raise capacity and reveal the next tight stage.

highlighted = computed this step

Improve Pack

Pack capacity changes from 4 to 7 units per hour.

Pack=7\text{Pack}=7
Improve PackAfter Pack is improved, Prep becomes the new bottleneck.Pack improveddemand 8/houroutput 6/hourunmet 2/hourPrepcapacity 6/hutil 1bottleneckPackcapacity 7/hutil 6/7Shipcapacity 8/hutil 3/4

New bottleneck

After the improvement, Prep is the bottleneck at 6 units per hour.

new bottleneck=Prep\text{new bottleneck}=\text{Prep}
Improve PackAfter Pack is improved, Prep becomes the new bottleneck.Pack improveddemand 8/houroutput 6/hourunmet 2/hourPrepcapacity 6/hutil 1bottleneckPackcapacity 7/hutil 6/7Shipcapacity 8/hutil 3/4

New output cap

The improved line can output 6 units per hour in this scenario.

output=6\text{output}=6
Improve PackAfter Pack is improved, Prep becomes the new bottleneck.Pack improveddemand 8/houroutput 6/hourunmet 2/hourPrepcapacity 6/hutil 1bottleneckPackcapacity 7/hutil 6/7Shipcapacity 8/hutil 3/4

What-if note

Improving one stage can move the bottleneck instead of removing every limit.

bottlenecks can move\text{bottlenecks can move}
Improve PackAfter Pack is improved, Prep becomes the new bottleneck.Pack improveddemand 8/houroutput 6/hourunmet 2/hourPrepcapacity 6/hutil 1bottleneckPackcapacity 7/hutil 6/7Shipcapacity 8/hutil 3/4